Hi all,
This is my first post, hope it works..!
My wife and I intend on opening a tanning salon, working up to 6 beds in Y1 (plus spray tan etc) and getting a new 3 phase connection is required. Through research / advice from electricians to run 6 beds, plus other standard salon electrical requirements concurrently, a 80kVA 3 phase connection would be required, running off 100A fuses. The eye watering part came from the quote via ENWL (Electricity North West);
Standard 3 phase 60kVA supply £6800
80kVA 3 phase supply £13230
Is this a standard cost that other salon owners have incurred?
Are there other salon owners on here with 5+ beds who can advise on what they do/did regarding 3 phase supply?
What I'd greatly appreciate is feedback from other salon owners who have been through the 3 phase journey. I'd hate to be missing something here and I've struggled to find a forum (other than this site) where I can pick the brains of those with experience.
I've also found, that to ensure 6 beds is achievable on that 3phase supply, they need to have a power consumption of 9kW, such as a Ergoline 400 Inspiration. Once you start moving up to the 'jazzy' beds using 15-18kW, 4 - 5 beds is your limit, even on the 80kVA supply. The 90kVA supply cost is around £20,000...so we can forget that.
Thank you for taking the time to read my post and I look forward to receiving advice / feedback.
This is my first post, hope it works..!
My wife and I intend on opening a tanning salon, working up to 6 beds in Y1 (plus spray tan etc) and getting a new 3 phase connection is required. Through research / advice from electricians to run 6 beds, plus other standard salon electrical requirements concurrently, a 80kVA 3 phase connection would be required, running off 100A fuses. The eye watering part came from the quote via ENWL (Electricity North West);
Standard 3 phase 60kVA supply £6800
80kVA 3 phase supply £13230
Is this a standard cost that other salon owners have incurred?
Are there other salon owners on here with 5+ beds who can advise on what they do/did regarding 3 phase supply?
What I'd greatly appreciate is feedback from other salon owners who have been through the 3 phase journey. I'd hate to be missing something here and I've struggled to find a forum (other than this site) where I can pick the brains of those with experience.
I've also found, that to ensure 6 beds is achievable on that 3phase supply, they need to have a power consumption of 9kW, such as a Ergoline 400 Inspiration. Once you start moving up to the 'jazzy' beds using 15-18kW, 4 - 5 beds is your limit, even on the 80kVA supply. The 90kVA supply cost is around £20,000...so we can forget that.
Thank you for taking the time to read my post and I look forward to receiving advice / feedback.